Current Schedule - Construction has begun.
Construction Update!
The Torrence Creek Tributary #1 stream restoration project is moving into the Wynfield areas. The contractor will be working on the creek upstream (north) of Wynfield Creek Parkway for the next 4 to 6 weeks. Here is what you can expect:
- Seeing and hearing construction equipment and crews working in the area.
- Clearing brush around the creek allowing the contractor to gain access to stabilize the creek’s bed and banks.
- The construction team working to preserve and save as many large trees along the creek and adjacent areas as possible.
Work over the next few months will include re-shaping the stream and planting native seed. However, the contractor will come back in the fall/winter to plant the trees and shrubs to ensure better survival.
We ask that you continue to help us maintain a safe work zone by keeping children and pets out of the active construction areas. We will continue to update you as the project moves forward. If you would like more information please visit this project website or contact us using the information below.
| Contractor: |
Eagle Wood Inc.
Bill Anderson
Denver, NC 28037
|
| Funding Agency: |
Mecklenburg County Storm Water Services
David Woodie, P.E., CPSWQ
704-336-3873
David.Woodie@MecklenburgCountyNC.gov
|
| Engineer: |
Kimley-Horn and Associates, Inc.
Jason Diaz, P.E., CFM
704-954-7464
jason.diaz@kimley-horn.com
|
| Bid Opening: |
March 20, 2012
|
| Contractor Notice to Proceed: |
April 17, 2012
|
| Construction End Date: |
Feb 2013
|
| |
| Construction in Wynfield Area is anticipated to take place between July and Oct 2012 |
| |
| Planting: |
Nov 2012 - Feb 2013
|
| Current Status: |
Surveyors are staking out project and utility locates have begun. Contractor has begun mobilizing to the project site and begun some clearing and grubbing of vegetation. The Contractor will begin construction at I-77 and work downstream to Stumptown road.
|
| Next Phase: |
Contractor will work from Stumptown Road to Wynfield Creek Parkway.
|
| |
Previous Items |
| Informal “Back Yard” Meetings with Wynfield Creek Residents (Click to Show/Hide) |
| September 7, 2011 @ 6:00 PM |
Stonegreen Lane and Cumbria Court (Meet in Stonegreen Lane cul-de-sac) |
| September 8, 2011 @ 7:15 PM |
Middlethorpe Lane (Meet in northern Middlethorpe Lane cul-de-sac) |
| September 8, 2011 @ 6:00 PM |
Bishopstone Court, Ledbury Court, and Charterhouse Lane (Meet at Bishopstone Court cul-de-sac) |
| The purpose of the meetings will be to update the residents that border the planned stream restoration/stabilization corridor on the current project status and to seek input from these residents. |
|
|
| April 2011 - January 2012 |
Planning, design, permitting, and public outreach |
| |
|
|
|
|